Rolling out new fixtures across a multi-store retail estate is one of the most operationally demanding tasks in retail implementation. Whether it is new gondola shelving for a supermarket chain, branded display units for a cosmetics brand, or freestanding furniture for a fashion retailer, the challenge is the same: delivering the right fixtures to the right stores, in the right condition, at the right time — and installing them to a consistent standard across every single location.
The stakes are high. A fixture rollout that goes wrong creates a cascade of problems: delayed store openings, empty selling space, damaged brand perception, and costly revisits. The concept of "first-time-right" delivery is not aspirational in fixture rollouts — it is a commercial necessity. Every store that requires a return visit doubles the cost and halves the goodwill with the retailer.
In this article, we walk through the end-to-end process of planning and executing a multi-store fixture rollout, drawing on our experience of delivering programmes across hundreds of UK retail locations.
The Unique Challenges of Fixture Rollouts
Fixtures are not like point-of-sale materials or promotional stock. They are large, heavy, often fragile, and frequently require specialist tools and skills to install. A single gondola bay might weigh 80 kilograms and arrive as a flat-pack of 15 or more individual components. A bespoke display unit designed by a creative agency might feature glass shelves, integrated lighting, and precision-machined fittings that demand careful assembly.
The challenges multiply with scale. Installing one fixture in one store is a straightforward task. Installing 500 fixtures across 200 stores, in a four-week window, while those stores continue to trade — that is a logistics and project management exercise of considerable complexity.
- Volume and weight: Fixtures require larger vehicles and more delivery resource than standard POS campaigns
- Fragility: Glass panels, polished surfaces, and precision components are vulnerable to transit damage
- Assembly complexity: Many fixtures require skilled installation, not just placement
- Store variation: No two stores are identical — floor plans, wall types, ceiling heights, and access points all differ
- Trading constraints: Most installations must happen outside peak trading hours, often overnight or in the early morning
- Coordination: Delivery and installation must be synchronised, and both must align with the store's own operational schedule
Site Surveys: The Foundation of a Successful Rollout
Every reliable fixture rollout begins with site surveys. These are not optional — they are the foundation upon which the entire delivery and installation plan is built. Skipping or rushing the survey stage is the single most common cause of rollout failure.
A thorough site survey captures the physical reality of each store location. Floor plans provided by head office are a starting point, but they are rarely accurate down to the centimetre — and in fixture installation, centimetres matter. Walls may have been moved, columns may obstruct planned fixture positions, electrical sockets may not be where the drawings suggest, and floor surfaces may vary between stores.
An effective site survey for a fixture rollout should capture:
- Precise measurements of the fixture zone, including ceiling height, wall width, and floor condition
- Location and type of existing fixings (wall plugs, floor bolts, bracket rails)
- Access route from delivery point to installation zone (doorway widths, corridor turns, lift dimensions)
- Electrical and data points relevant to the fixture (lighting, digital screens, sensor connections)
- Any obstructions or hazards (sprinkler heads, fire exits, structural columns, underfloor heating)
- Photographic evidence of the current state, taken from standardised angles
- Store-specific delivery restrictions (loading bay availability, time windows, parking constraints)
"We have seen rollouts where the design team specified a 1.8-metre-wide fixture unit for stores where the actual available wall space was 1.6 metres. Without a survey, that problem only surfaces when the installation team is on-site with the wrong fixture — and by then, you have wasted a delivery, a labour call, and the store's patience."
Survey data should be compiled into a store-by-store installation brief that the delivery team and the field installation crew can reference. This brief becomes the single source of truth for every decision made during the rollout.
Fixture Specifications and Pre-Production Checks
Before a single fixture leaves the warehouse, the specification must be locked down and validated. This means working with the design studio or manufacturer to confirm every detail: materials, finishes, dimensions, component counts, assembly sequences, and fixing methods.
Pre-production checks — ideally conducted at the manufacturer's facility — verify that the fixtures being produced match the approved design. A prototype or first-off sample should be fully assembled, inspected, and signed off before the production run begins. This catches issues such as colour inconsistencies between batches, structural weaknesses, or assembly steps that are impractical in a live store environment.
Common specification issues that surface during fixture rollouts include:
- Fixings supplied do not suit the wall type in certain stores (e.g., plasterboard anchors provided for brick walls)
- Assembly instructions assume two people, but the fixture actually requires three for safe handling
- Electrical components are not PAT tested or lack the required certification labels
- Packaging is insufficient for the transit method, leading to predictable damage patterns
- Component counts are wrong — screws, brackets, or shelf clips are short-packed
Each of these issues is preventable with proper pre-production validation. The cost of catching a problem at the factory is a fraction of the cost of discovering it at store 47 of a 200-store rollout.
Delivery Scheduling and Installation Sequencing
The delivery schedule for a fixture rollout is not simply a list of addresses and dates. It is a carefully constructed sequence that accounts for geographic efficiency, store trading patterns, installation team availability, and the retailer's own operational calendar.
Most fixture rollouts are sequenced in geographic waves. A typical pattern might begin in one region, with installation teams working through a cluster of stores before moving to the next region. This minimises travel time and accommodation costs for the field teams, and it allows the project management team to refine processes based on early installations before scaling to the full estate.
Delivery and installation must be tightly synchronised. Fixtures delivered too early create storage problems in stores that rarely have back-of-house space to spare. Fixtures delivered too late leave installation teams idle and push the programme behind schedule. The ideal scenario is a just-in-time delivery model where fixtures arrive at the store within hours of the installation team, not days.
"Sequencing is where rollouts are won or lost. You need to consider school holidays, bank holidays, store promotional calendars, staff availability, and even local events that might affect access. A fixture delivery scheduled for a Saturday morning in a shopping centre hosting a Christmas market is not going to end well."
Dealing with Store Variations
One of the defining challenges of multi-store rollouts is that no two stores are the same. Even within a single retailer's estate, stores vary enormously in layout, age, construction, and operational character.
Floor plans differ. A flagship high-street store will have a completely different layout from a retail park unit or a concession within a department store. The same fixture may need to be wall-mounted in one location, freestanding in another, and adapted to fit a curved wall in a third.
Access restrictions vary. Some stores have goods lifts that can accommodate a full pallet; others have narrow staircases and doorways that require fixtures to be carried in piece by piece. City-centre stores may have loading restrictions that limit deliveries to specific time windows. Shopping centre management may require advance booking of service corridors and goods lifts.
Trading hours create constraints. Most retailers will not accept fixture installations during peak trading periods. This often means overnight working, early-morning slots before the store opens, or installations scheduled on the store's quietest trading day. Each store may have different preferences, and the rollout schedule must accommodate them all.
The key to managing store variation is the site survey data combined with clear communication between the rollout coordinator, the store manager, and the installation team. Every store should have a bespoke installation plan — even if the fixture itself is standard across the estate.
Quality Standards, Snagging, and Sign-Off
Quality control in a fixture rollout operates at two levels: the quality of the fixture itself (addressed during manufacturing QC and warehouse receiving) and the quality of the installation (addressed on-site during and after the build).
Installation quality standards should be defined before the rollout begins, documented in a quality checklist, and communicated to every member of the field team. A typical fixture installation quality checklist includes:
- Fixture is level, plumb, and securely fixed to the wall or floor
- All shelves and components are correctly positioned per the planogram
- No visible damage — scratches, chips, dents, or marks
- Electrical components are functioning (lighting, screens, sensors)
- All packaging, waste, and protective materials have been removed and disposed of
- The surrounding area has been left clean and undamaged
- Photographic evidence has been captured from standardised angles (before, during, and after installation)
Snagging — the process of identifying and rectifying defects — should happen immediately after installation, not days or weeks later. The installation team should conduct a self-inspection before leaving the store, and the store manager (or a designated representative) should review and sign off the completed work. Any snags should be logged, photographed, and assigned a resolution timeframe.
A formal sign-off process protects both the implementation partner and the client. It creates a clear record of what was delivered, to what standard, and with what exceptions. Without sign-off, disputes about installation quality become subjective arguments rather than evidence-based discussions.
Coordinating with Store Teams
The relationship between installation teams and store teams is critical to rollout success. Installation crews are guests in someone else's workplace, and the way they conduct themselves directly affects the retailer's willingness to support future programmes.
Advance communication with store managers is essential. Each store should receive a briefing pack that includes the installation date, the expected duration, what the team will need (access to power, clear space, goods lift booking), and who to contact if there are problems. The store manager should know exactly what to expect and should have the opportunity to flag any concerns before the installation day.
On the day, the installation team lead should introduce themselves to the duty manager, confirm the plan, and agree on any ground rules (noise restrictions, areas that must remain accessible, break times). Professional conduct — clean workwear, tidy work areas, respectful communication — is not a nice-to-have; it is a requirement.
Managing Returns and Damaged Units
Even with the best planning, some fixtures will arrive damaged, some will not fit specific store configurations, and some stores will reject installations that do not meet their standards. A robust returns process is essential.
Damaged fixtures identified during delivery should be photographed, reported, and returned to the warehouse for assessment. If a replacement is available, it should be dispatched immediately to avoid delaying the installation. If not, the store should be rescheduled and moved to the end of the rollout wave to allow time for a replacement to be sourced.
"Every rollout needs a contingency plan for damaged units. We typically hold a buffer stock of 5-10% above the required fixture count. It costs a little more upfront, but it means we can replace damaged units on the spot rather than pausing the entire programme while replacements are manufactured."
Returns logistics should be built into the rollout plan from the outset, not treated as an afterthought. This includes defining who is responsible for return transport costs, where damaged units will be stored pending assessment, and what the process is for claiming against the manufacturer or carrier.
At The Wild Axis Group, we approach every fixture rollout with the expectation that things will not go perfectly — because in a programme spanning hundreds of stores, they never do. What matters is how quickly and effectively problems are resolved. Our planning methodology, our survey process, our quality controls, and our contingency protocols are all designed to deliver first-time-right results at scale. And when issues do arise, we have the systems and the people in place to fix them fast.